Job shop quoting

Price the setup into the machining quote.

Estimate the machine-time component of a job, then check which costs your quoting workflow still needs to capture.

At a glance
  1. SetupPer-run preparation
  2. MachiningCycle time × quantity
  3. QuoteRates and additional costs

Separate the costs that move with batch size

Break the routing into quoted operations

Estimate setup and cycle time separately for turning, milling and any other operations you quote. Assign each operation a rate for the appropriate resource. Note whether the shop rate already includes labour and overhead so costs are included once.

Spread setup over the run

At ₹1,200 per hour, a 60-minute setup and 50 parts at six minutes each totals ₹7,200 in machine time, or ₹144 per piece. If the order is split into two runs with a setup each time, include both setups in the estimate.

Review what the estimate excludes

Add purchased material, consumable tooling, outside processes, inspection, packing and expected yield effects as applicable. Revisit the estimate after the first run using recorded setup and cycle time. Capture the reason for large deviations so the next quote has a usable starting point.

Machining cost per piece

Estimate machine time cost per planned piece for one operation and one setup. Add material, scrap allowance and any other costs separately.

Formula · [(setup minutes + cycle minutes × quantity) ÷ 60] × hourly rate ÷ quantity

Explore Envisage ERP

Envisage ERP describes engineering product cost estimation and detailed cost breakdowns. Bring a repeat job and ask to see the quotation assumptions alongside its production actuals.